Question: answer this question please ASAP A 4.7 hours B 5.5 Hours C 6.9 Hours D 3.4 Hours E 4.3 Hours TB MC Qu. 075-49 A

answer this question please ASAP
A 4.7 hours
B 5.5 Hours
C 6.9 Hours
D 3.4 Hours
E 4.3 Hours answer this question please ASAP A 4.7 hours B
TB MC Qu. 075-49 A company is preparing a bid on a... A company is preparing a bid on a government contract for 40 units of a certain product. The operations Manager estimates the assembly time required for the first two units to be 10.4 hours and 8.8 hours. Approximately how long will it take to produce the fifteenth unit? Multiple Choice 47 hours 5.5 hours 69 hours A MacBook Air