Question: Answer this question. Several answers can be correct. In project management the following holds: 1 ) CPM assumes fixed deterministic activity times 2 ) Critical
Answer this question. Several answers can be correct.
In project management the following holds:
CPM assumes fixed deterministic activity times
Critical path represent a series of activities that run through the whole process and the sum of their times equals the total project time
Earliest start generally represents the latest time at which an activity needs to start to prevent the delays in the project as a whole.
Using PERT method we can derive the probability that the project will be finished on time
Critical activities are activities with largest slack time