Question: Answer this question. Several answers can be correct. In project management the following holds: 1 ) CPM assumes fixed deterministic activity times 2 ) Critical

Answer this question. Several answers can be correct.
In project management the following holds:
1) CPM assumes fixed deterministic activity times
2) Critical path represent a series of activities that run through the whole process and the sum of their times equals the total project time
3) Earliest start generally represents the latest time at which an activity needs to start to prevent the delays in the project as a whole.
4) Using PERT method we can derive the probability that the project will be finished on time
5) Critical activities are activities with largest slack time

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!