Answering the following question based on the Weighted Scoring Model below. Criteria Weight Project 1 Project 2
Question:
Answering the following question based on the Weighted Scoring Model below.
Criteria | Weight | Project 1 | Project 2 | Project 3 | Project 4 |
---|---|---|---|---|---|
Supports Key Business Objectives | 25% | 90 | 90 | 50 | 20 |
Has Strong Internal Sponsor | 15% | 70 | 90 | 50 | 20 |
Has Strong Customer Support | 15% | 50 | 90 | 50 | 20 |
Uses Realistic Level of Technology | 10% | 25 | 90 | 50 | 70 |
Can be Implemented in one year or less | 5% | 20 | 20 | 50 | 90 |
Provides Positive NPV | 20% | 50 | 70 | 50 | 50 |
Has Low Risk in Meeting Scope, Tiem and Cost goals | 10% | 20 | 50 | 50 | 90 |
Weighted Project Scores | 100% | 56 | 78.5 | 50 | 41.5 |
a. What is the most important Criterion?
b. What is the 2nd most important Criterion?
c. Which project is the best project to select for implementation?
d. Which project is the 2nd best project to select for implementation?