Question: any one answer this asap Predecessor None None Activity B C D E F G AB D C EF Normal time 3 4 1 3
any one answer this asap
Predecessor None None Activity B C D E F G AB D C EF Normal time 3 4 1 3 2 6 5 Crash time 2 3 1 2 1 2 Normal cost crash cost 200.001 400 00 300.00 600.00 300.00 14 500.000 550.00 500.00 900.00 700.00 1.500.00 150.00 250.00 Hereby the data for a project, with the time in days and the costs include both direct and indirect costs. Draw the network diagram A What is the critical path? (3 points) 8. What is the project completion time and project total cost? (2 points) C. Your dient needs you to reduce the total time by three days - cost-efficient as possible, of course! What is the new critical path and total cost in this new situation? (5 points)