You are in charge of a project at the local community center. The center needs to...
Fantastic news! We've Found the answer you've been seeking!
Question:
Transcribed Image Text:
You are in charge of a project at the local community center. The center needs to remodel one of the rooms in time for the start of a new program. Delays in the project mean that the center must rent other space at a nearby church at additional cost. Time and cost data for your project are contained in the table below. Your interest is in minimizing the cost of the project to the community center. Activity START A B C D E F G H FINISH Normal Time (days) 0 8 7 3 8 5 8 4 6 0 Normal Cost (S) 0 50 40 70 20 30 80 50 60 D Crash Time (days) 0 7 3 1 6 5 A 1 4 0 Crash Cost ($) Immediate Predecessor(s) 0 180 360 310 100 30 520 320 100 a. Using the normal times for each activity, what is the earliest date you can complete the project? The corresponding project duration using the normal times is 22 days. (Enter your response as an integer.) b. Suppose the variable overhead costs are $30 per day for your project. Also, suppose that the center must pay $80 per day for a temporary room on day 17 or beyond. Find the minimum-cost project schedule. Fill in the table below to show the proper schedule (time for each activity after crashing) for completing the project at minimum cost. (Enter your responses as integers.) Activity Time (days) Activity Time (days) A 8 E B F D G H L START START B A, C A.C B D E. F G, H E You are in charge of a project at the local community center. The center needs to remodel one of the rooms in time for the start of a new program. Delays in the project mean that the center must rent other space at a nearby church at additional cost. Time and cost data for your project are contained in the table below. Your interest is in minimizing the cost of the project to the community center. Activity START A B C D E F G H FINISH Normal Time (days) 0 8 7 3 8 5 8 4 6 0 Normal Cost (S) 0 50 40 70 20 30 80 50 60 D Crash Time (days) 0 7 3 1 6 5 A 1 4 0 Crash Cost ($) Immediate Predecessor(s) 0 180 360 310 100 30 520 320 100 a. Using the normal times for each activity, what is the earliest date you can complete the project? The corresponding project duration using the normal times is 22 days. (Enter your response as an integer.) b. Suppose the variable overhead costs are $30 per day for your project. Also, suppose that the center must pay $80 per day for a temporary room on day 17 or beyond. Find the minimum-cost project schedule. Fill in the table below to show the proper schedule (time for each activity after crashing) for completing the project at minimum cost. (Enter your responses as integers.) Activity Time (days) Activity Time (days) A 8 E B F D G H L START START B A, C A.C B D E. F G, H E
Expert Answer:
Answer rating: 100% (QA)
Activity A B Time days 8 6 Normal Cost 50 60 Crash Cost 100 80 Crash ... View the full answer
Related Book For
Operations management processes and supply chain
ISBN: 978-0136065760
9th edition
Authors: Lee J Krajewski, Larry P Ritzman, Manoj K Malhotra
Posted Date:
Students also viewed these accounting questions
-
you will be given three errors that may or may not affect the trial balance. You are to determine the following: 1. As a result of each error, will the trial balance still balance? Consider each...
-
You are in charge of a project at the local community center. The center needs to remodel one of the rooms in time for the start of a new program. Delays in the project mean that the center must rent...
-
What is path dependence? Explain the concept using your own words and provide an example of path dependence (other than what we have already mentioned in class). List the 4 categories of innovation,...
-
Refer to the data in Exercise 3-12. Prepare the adjusted trial balance for Event Planners for March 31, 2017. The remaining account balances you require (after adjustments) are as follows: Cash...
-
(a) A compound U (C9H10O) gives a negative iodoform test. The IR spectrum of U shows a strong absorption peak at 1690 cm-1. The 1H NMR spectrum of U gives the following: Triplet...
-
Which of the following are debt investments an entity has both the positive intent and the ability to hold till maturity? a. Trading securities. b. Call options. c. Available-for-sale securities. d....
-
Amoruso Co. produces and distributes semiconductors for use by computer manufacturers. Amoruso Co. issued $7,500,000 of 15-year, 10% bonds on April 1 of the current year at face value, with interest...
-
Types of recruitment In the past, the recruitment process was a reactive one in which companies did not necessarily conduct an analysis of the type of strategy they would use to recruit candidates....
-
Kaitlyn purchased a life annuity contract with $450,000 she inherited. She began receiving $2,400 per month on April 1, 2022 when she was age 60. How much of each payment received by Kaitlyn is...
-
What is a separation agreement?
-
What is a collaborative divorce? How is it similar to and different from other alternative dispute resolution approaches?
-
How fast must a helium atom move in order to have a de Broglie wavelength of \(1.5 \times 10^{-10} \mathrm{~m}\) ?
-
Explain the differences between the two important approaches to mediation, the problem-solving model and the transformative model.
-
What is e-mediation? What possible advantages does it offer over faceto-face mediation? What are its possible limitations?
-
Let y = e5z + sin(x2). Then equals (a) 5eb + cos(x) (e) none of these (b) ebr +2x cos(x2) (c) ebz + cos(r) (d) 5e + 2x cos(r2)
-
Which internal control principle is especially diffi cult for small organizations to implement? Why?
-
Canon, a Japanese manufacturer of photographic equipment, decided against offshoring and kept its manufacturing and new product development processes in Japan, which has relatively high labor costs,...
-
Compare and contrast the following two situations: a. A companys lean system stresses teamwork. Employees feel more involved and, therefore, productivity and quality increase at the company. The...
-
Build-Rite Construction has received favorable publicity from guest appearances on a public TV home improvement program. Public TV programming decisions seem to be unpredictable, so Build Rite cannot...
-
Pegasus Veterinary Hospital (PVH) is a partnership of five veterinarian surgeons who specialize in treating horses. PVH is located in a $25 million facility on 20 acres of land, employing over 40...
-
A tender evaluation method specifies 60% price and 40% quality. What is the weighted score of a tender that scored 80 points (out of 100) for price and 60 for quality?
-
You are a recently appointed purchasing manager who is overseeing terms and con- ditions of contract for an important international purchase with a UN country. What rules should you be particularly...
Study smarter with the SolutionInn App