Question: AON network diagram: B E A G H TI A B D E F G H Activity Normal Time (weeks) 4 3 2 4 6

AON network diagram: B E A G H TI A B D E F G HAON network diagram: B E A G H TI A B D E F G H

AON network diagram: B E A G H TI A B D E F G H Activity Normal Time (weeks) 4 3 2 4 6 3 2 Using the information given, (a) Calculate the completion time for this project. Project completion time = weeks. (b) Identify the activities on the critical path. Critical activities: ACEGH ABEGFD ADFCEB ADFGH ACFGH ABEGH