Question: AON Network ModelFrom the following information, develop an AON project network and answer the following questions.Thanks. ID Description Predecessor Time A Survey site None 4
AON Network ModelFrom the following information, develop an AON project network and answer the following questions.Thanks.

ID Description Predecessor Time A Survey site None 4 B Excavate site A 4 Install power lines B 4 Install drainage B Pour foundation C. D 2 The project will take days The critical path is The late start on Activity C is days The slack on Activity C is days. The slack on Activity D is days The early start on Activity E is days