Question: From the following information, develop an AON project network and answer the questions. The earliest completion time for this project is ________ days. Use the

From the following information, develop an AON project network and answer the questions.

The earliest completion time for this project is ________ days.

Use the previous project network. The Early Finish (EF) time for Activity D Excavate Site is ________ days.

Use the previous project network. The Early Start (ES) time for Activity E Pour Foundation Lines is ________ days.

Use the previous project network. The Slack (ST) time for Activity B Install Drainage is ________ day(s).

Use the previous project network. Critical activities are Activities ________.

Use the previous project network. The largest amount of slack that any activity has in this project is ________days.

Use the previous project network. If Activity D Excavate Site is delayed by 2 days, then the revised earlier project completion time is ________ days.

Activity ID Description Predecessor Time (days)
A Survey Site None 2
B Install Drainage A 5
C Install Power Lines A 3
D Excavate Site B, C 5
E Pour Foundation D

6

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!