Question: From the following information, develop an AON project network and answer the questions. The earliest completion time for this project is ________ days. Use the
From the following information, develop an AON project network and answer the questions.
The earliest completion time for this project is ________ days.
Use the previous project network. The Early Finish (EF) time for Activity D Excavate Site is ________ days.
Use the previous project network. The Early Start (ES) time for Activity E Pour Foundation Lines is ________ days.
Use the previous project network. The Slack (ST) time for Activity B Install Drainage is ________ day(s).
Use the previous project network. Critical activities are Activities ________.
Use the previous project network. The largest amount of slack that any activity has in this project is ________days.
Use the previous project network. If Activity D Excavate Site is delayed by 2 days, then the revised earlier project completion time is ________ days.
| Activity ID | Description | Predecessor | Time (days) |
|---|---|---|---|
| A | Survey Site | None | 2 |
| B | Install Drainage | A | 5 |
| C | Install Power Lines | A | 3 |
| D | Excavate Site | B, C | 5 |
| E | Pour Foundation | D | 6 |