Question: Appendix 1 < Passenger Forecasts > Passenger Forecasts for the New Gate Area at Newark ( To be used for facility and manpower planning )
Appendix Passenger Forecasts
Passenger Forecasts for the New Gate Area at Newark
To be used for facility and manpower planning
Description Mon Tue Wed Thu Fri Sat Sun
Total between AM and PM
Total between PM and PM
Peak hour Traffic
Notes:
The passenger forecasts for all flights departing Newark in the morning
and the evening shifts has been combined together to show daily total
load in each shift. The results have been rounded to the nearest one
hundred.
Use peak hour traffic to design the passenger checkin area at the gates.
The seating area should have enough capacity to accommodate the peak
number of passengers.
The number of EcoJet agents customer service personnel in the newly
built gate area will depend upon the total traffic during the eight hour shift.
The current rule of using one customer service personnel to handle one
hundred departures during an eight hour shift seems to be working well.
There is plenty of slack time built into these estimates for coffee and lunch
breaks.
It is important to note that in real life situation, a significant amount of effort is
required in collecting the data by examining various documents and
interviewing different people, developing assumptions to simplify the
analysis, and presenting the data in an understandable form.
Appendix
Summary of Costs
Prepared by Accounting
After several meetings with vendors, the fixed cost and the variable cost
proposed by each of the three vendors have been finalized. The results are
shown in the table below.
Fixed Costs Variable Costs
American Airport Construction, Inc. $ $
National Airport Contracting Corp. $ $
Newark Airport Construction Corp $ $
Notes:
The fixed costs for each vendor include all flooring, wall paneling,
ceiling, electrical, telecom wiring, and plumbing work.
The tasks to be performed by each vendor and the time estimates for
completing each tasks have been finalized. In order to permit an
Apple to Apple comparison of costs, all three vendors were asked to
use the same time estimates.
EcoJet will need to supply the final plans for wiring, electrical work,
network jacks, and plumbing plans.
EcoJet will also be responsible for acquisition of chairs, tables, ticket
counters, fixtures, and other furniture. The vendor will be responsible
for all installation.
All three vendors have worked with EcoJet before and there is no
significant difference between dependability and quality of vendors.
The total variable costs will depend upon the peak hour design
capacity of the gate area expressed in terms of the maximum number
of passenger departures per hour.
It is important to note that in real life situation, a significant amount of effort is
required in collecting the data by examining various documents and interviewing
different people, developing assumptions to simplify the analysis, and presenting
the data in an understandable form.
Appendix
Major Tasks and Completion Time
Prepared in Conjunction with Vendors
The major tasks required to be completed for finishing the gate area at
Newark Airport has been determined with the help of vendors and EcoJet
operations personnel.
Task
ID
Description of Tasks Immediate
Predecessors
a m b Responsible
Party
A Award Contract to Vendor EcoJet
B Finalize Telecom Wiring Plan EcoJet
C Finalize Electrical & Plumbing Plan EcoJet
D Prepare Rough floors and walls A Vendor
E Acquire all furniture and fixtures A B C EcoJet
F Install telecom wiring as planned B D Vendor
G Install electrical wiring as planned C D Vendor
H Install rough plumbing as planned C D Vendor
I Finish walls E F G H Vendor
J Finish Floors D Vendor
K Install furniture and counters F G J Vendor
L Install telecom and network jacks K Vendor
M Finish plumbing work I Vendor
N Finish Electrical work I, K Vendor
O Test all computers L N EcoJet
P Test phones, announcements etc. L N EcoJet
Q Inspect entire premises M O P EcoJet
R Project Completion & Signoff Q EcoJet
Notes:
a represents the optimistic time in days to perform a task.
m represents the most likely time in days to perform a task.
b represents the pessimistic time in days to perform a task.
The time estimates remain the same for all three vendors.
It is important to note that in real life situation, a significant amount of effort is
required in collecting the data by examining various documents and interviewing
different people, developing assumptions to simplify the analysis, and presenting
the data in an understandable form.
Appendix
Flight Delay Statistics
Prepared by Flight Operati
Step by Step Solution
There are 3 Steps involved in it