Question: Appendix 1 < Passenger Forecasts > Passenger Forecasts for the New Gate Area at Newark ( To be used for facility and manpower planning )

Appendix 1< Passenger Forecasts>
Passenger Forecasts for the New Gate Area at Newark
(To be used for facility and manpower planning)
Description Mon Tue Wed Thu Fri Sat Sun
Total between 6 AM and 2 PM 800600500600700200400
Total between 2 PM and 10 PM 700400500700900300700
Peak hour Traffic 175150150150200100175
Notes:
1. The passenger forecasts for all flights departing Newark in the morning
and the evening shifts has been combined together to show daily total
load in each shift. The results have been rounded to the nearest one
hundred.
2. Use peak hour traffic to design the passenger check-in area at the gates.
The seating area should have enough capacity to accommodate the peak
number of passengers.
3. The number of Eco-Jet agents (customer service personnel) in the newly
built gate area will depend upon the total traffic during the eight hour shift.
4. The current rule of using one customer service personnel to handle one
hundred departures during an eight hour shift seems to be working well.
There is plenty of slack time built into these estimates for coffee and lunch
breaks.
It is important to note that in real life situation, a significant amount of effort is
required in collecting the data by examining various documents and
interviewing different people, developing assumptions to simplify the
analysis, and presenting the data in an understandable form.
Appendix 2
Summary of Costs
(Prepared by Accounting)
After several meetings with vendors, the fixed cost and the variable cost
proposed by each of the three vendors have been finalized. The results are
shown in the table below.
Fixed Costs Variable Costs
American Airport Construction, Inc. $800,000 $1500
National Airport Contracting Corp. $900,000 $1200
Newark Airport Construction Corp $700,000 $1800
Notes:
The fixed costs for each vendor include all flooring, wall paneling,
ceiling, electrical, telecom wiring, and plumbing work.
The tasks to be performed by each vendor and the time estimates for
completing each tasks have been finalized. In order to permit an
Apple to Apple comparison of costs, all three vendors were asked to
use the same time estimates.
Eco-Jet will need to supply the final plans for wiring, electrical work,
network jacks, and plumbing plans.
Eco-Jet will also be responsible for acquisition of chairs, tables, ticket
counters, fixtures, and other furniture. The vendor will be responsible
for all installation.
All three vendors have worked with Eco-Jet before and there is no
significant difference between dependability and quality of vendors.
The total variable costs will depend upon the peak hour design
capacity of the gate area expressed in terms of the maximum number
of passenger departures per hour.
It is important to note that in real life situation, a significant amount of effort is
required in collecting the data by examining various documents and interviewing
different people, developing assumptions to simplify the analysis, and presenting
the data in an understandable form.
Appendix 3
Major Tasks and Completion Time
(Prepared in Conjunction with Vendors)
The major tasks required to be completed for finishing the gate area at
Newark Airport has been determined with the help of vendors and Eco-Jet
operations personnel.
Task
ID
Description of Tasks Immediate
Predecessors
a m b Responsible
Party
A Award Contract to Vendor 224 Eco-Jet
B Finalize Telecom Wiring Plan 235 Eco-Jet
C Finalize Electrical & Plumbing Plan 123 Eco-Jet
D Prepare (Rough) floors and walls A 121620 Vendor
E Acquire all furniture and fixtures A, B, C 222 Eco-Jet
F Install telecom wiring as planned B, D 111419 Vendor
G Install electrical wiring as planned C, D 81012 Vendor
H Install rough plumbing as planned C, D 346 Vendor
I Finish walls E, F, G, H 777 Vendor
J Finish Floors D 333 Vendor
K Install furniture and counters F, G, J 121418 Vendor
L Install telecom and network jacks K 345 Vendor
M Finish plumbing work I 222 Vendor
N Finish Electrical work I, K 333 Vendor
O Test all computers L, N 125 Eco-Jet
P Test phones, announcements etc. L, N 234 Eco-Jet
Q Inspect entire premises M, O, P 111 Eco-Jet
R Project Completion & Sign-off Q 111 Eco-Jet
Notes:
a represents the optimistic time in days to perform a task.
m represents the most likely time in days to perform a task.
b represents the pessimistic time in days to perform a task.
The time estimates remain the same for all three vendors.
It is important to note that in real life situation, a significant amount of effort is
required in collecting the data by examining various documents and interviewing
different people, developing assumptions to simplify the analysis, and presenting
the data in an understandable form.
Appendix 4
Flight Delay Statistics
(Prepared by Flight Operati

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!