Question: Apples are prepared in a two step process with two sequential resourcesThe processing time the first resource is 4 2 seconds and for the second
Apples are prepared in a two step process with two sequential resourcesThe processing time the first resource is seconds and for the second resource it is secondsThe first resource has worker and the second resource has worker What is the capacity of this process in terms of apples per minute? Note: Round your answer to decimal places