Question: Application 2 - Class Consider the following Project begin{tabular}{|l|l|l|} hline Activity & begin{tabular}{l} Immediate Predecessors end{tabular} & TIME (Weeks) hline A & -

Application 2 - Class Consider the following Project \begin{tabular}{|l|l|l|} \hline Activity & \begin{tabular}{l} Immediate \\ Predecessors \end{tabular} & TIME (Weeks) \\ \hline A & - & 2 \\ \hline B & - & 3 \\ \hline C & A & 2 \\ \hline D & A, B & 4 \\ \hline E & C & 4 \\ \hline F & C & 3 \\ \hline G & D, E & 5 \\ \hline H & F, G & 2 \\ \hline \end{tabular} Application 2-Class Consider the following Project 1. Draw the project network? 2. Identify the critical path? 3. Calculate the Earliest and Latest start and Earliest and Latest finish for each activity? 4. Calculate the slack time at each activity
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts