Application 2-PERT For the following problems, diagram and then show ES, EF, LS, LF, and slack on a separate table. 7. Duration Activities Predecessors 0 m P A 1 14 15 B 4 6 8 C A, B 1 8 15 D A, B 9 9 9 E C 4 9 26 F C 1 2 9 G C 3 4 11 H D 7 9 11 I G, H 2 3 40 J E, F 5 5 5 K I, J 5 6 13