Question: Applications are evaluated in a two step process with two sequential resources. The processing time at the first resource is 1 1 0 minutes and
Applications are evaluated in a two step process with two sequential resources. The processing time at the first resource is minutes and for the second resource it is minutes. The first resource has workers and the second resource has worker.
What is the capacity of this process in terms of applications per hour?