Question: Applications are scanned in a two step process with two sequential resources. The processing time at the first resource is 9 . 1 minutes and

Applications are scanned in a two step process with two sequential resources. The processing time at the first resource is 9.1 minutes and for the second resource it is 12 minutes. The first resource has 2 workers and the second resource has 4 workers.
What is the capacity of this process in terms of applications per hour?