Question: Applications are the flow unit in a process with two resources. The processing times for the resources are 0.56 and 0.36 hours. Demand occurs at
Applications are the flow unit in a process with two resources. The processing times for the resources are 0.56 and 0.36 hours. Demand occurs at the rate 0.36 applications per hour.
What is the utilization % of the first resource?