Question: Apply critical path method to the project network shown below: Critical time is: Critical activities are: Critical path is: 10 3 2 7 8 5

Apply critical path method to the project network shown below:

Critical time is: Critical activities are: Critical path is:

Apply critical path method to the project network

10 3 2 7 8 5 Time ES EF LS LF TS Activity 1-2 11 2-3 6 2-4 4 2-5 3 3-6 10 4-7 5 5-7 7 6-7 4 s log 7-8 8

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!