Question: Aria is about to introduce a new product which involves six activities. Table 2 illustrates relevant information about each activity: its immediate predecessor ( s
Aria is about to introduce a new product which involves six activities. Table
illustrates relevant information about each activity: its immediate predecessors the
duration, the cost, the crash time and the crash cost.
Table Activity timecost data.
a Draw the project network for the problem.
b Determine the EST, EFT, LST LFT and slack for each activity. Also determine the
critical paths the total project completion time and the total cost of the project.
c Aria knows that the competitor's product is scheduled to hit the market days from
now, so Aria must introduce her new product within days. What should be done to
achieve this at the least possible cost? Calculate the cost of the crashed project.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock