Question: Arrival Time Burst Time (Milliseconds Process 0 15 P1 2 12 P2 4 9 P3 6 6 P4 8 3 P5 10 1 P6 Draw
| Arrival Time | Burst Time (Milliseconds | Process |
| 0 | 15 | P1 |
| 2 | 12 | P2 |
| 4 | 9 | P3 |
| 6 | 6 | P4 |
| 8 | 3 | P5 |
| 10 | 1 | P6 |
Draw a Gantt chart and find the average waiting time and average turnaround time using Round Robin Scheduling Algorithm(Time Quantum = 6 msec) using the following table :