Question: As a project is crashed and project duration is reduced, direct costs typically Multiple Choice A ) become unreliable. B ) increase. C ) stay

As a project is crashed and project duration is reduced, direct costs typically
Multiple Choice
A) become unreliable.
B) increase.
C) stay the same.
D) become unstable.
E) decrease.