Question: As a project is crashed and project duration is reduced, direct costs typically q , increase. become unstable. decrease. become unreliable. stay the same.
As a project is crashed and project duration is reduced, direct costs typically
increase.
become unstable.
decrease.
become unreliable.
stay the same.