Question: As a project manager, what project component should you focus on to minimize the likelihood of incurring changes to the project budget or extensions in
As a project manager, what project component should you focus on to minimize the likelihood of incurring changes to the project budget or extensions in the project timeline?
point
Team members
Retrospectives
Proposals
Scope