Question: As a project manager, you are aware that changes are bound to occur during projects. While monitoring and controlling change on your projects, you use
As a project manager, you are aware that changes are bound to occur during projects. While monitoring and controlling change on your projects, you use the term scope creep. What does the term refer to?
a) Uncontrolled expansion to product or project scope without adjustments to time, cost, and
resources
b) Controlled expansion to product or project scope without adjustments to time, cost, and
resources
c) Manageable expansion to product or project scope without adjustments to time, cost, and
resources