Question: As a project manager, you are responsible for managing all project costs. You are using several different analytical techniques to assess the expected project costs.
As a project manager, you are responsible for managing all project costs. You are using several different analytical techniques to assess the expected project costs. Which analytical technigue will produce a result in months and years? A) Payback period B) Internal rate of return C) Met present value D) Return on investment