Question: As a project manager you are using a fishbone diagram to find the potential risks on your project. Which process are you in ? Question
As a project manager you are using a fishbone diagram to find the potential risks on your project. Which process are you in
Question options:
Identify Risk
Plan Risk Response
Perform Qualitative Risk Analysis
Step by Step Solution