Question: As a project manager, you are working on a software development project for a client. Due to unforeseen circumstances, you are falling behind schedule and

As a project manager, you are working on a software development project for a client. Due to unforeseen circumstances, you are falling behind schedule and going over budget. After exhausting all other options, you decide to implement Scope Reduction. Which of the following steps should you take first? This question is required.*

A

Unilaterally decide which features to cut without consulting stakeholders.

B

Postpone the project deadline to give the team more time.

C

Discuss the situation with stakeholders and seek their input on reducing scope.

D

Reduce the number of team members to decrease labor costs.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!