Question: As a project manager, you have been asked during implementation to make cost and schedule trade - offs to obtain the greatest amount of schedule

As a project manager, you have been asked during implementation to make cost and schedule trade-offs to obtain the greatest amount of schedule compression for the least incremental cost. What technique should you select?
Question 2 options:
Crashing
Fast tracking
Delphi technique
Earned value management