Question: As a project manager you have the following data for your current project in a hospital. Expected Completion time 22 weeks Variance of the

As a project manager you have the following data for your current

As a project manager you have the following data for your current project in a hospital. Expected Completion time 22 weeks Variance of the project 4 weeks. What is the probability this project will take less than 23 weeks?

Step by Step Solution

3.30 Rating (153 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

To find the probability that the project will take less than 23 weeks ... View full answer