Question: Question 1. Question 2. Joe used a project management software package for a PERT project. It provided the following results: Expected project completion time =22
Question 1.

Question 2. 
Joe used a project management software package for a PERT project. It provided the following results: Expected project completion time =22 days Variance of project completion time =2.77 days ( Note: this is a variance, NOT a standard deviation ) What is the probability of completing the project in 21 days or less? 0.2743 0.3215 0.2257 0.7743 Joe used a project management software package for a PERT project. It provided the following results: Expected project completion time =22 days Variance of project completion time =2.77 days ( Note: this is a variance, NOT a standard deviation ) What is the probability the project will take over 21 days to complete? 0.7257 0.2257 0.2743 0.8215