As a project manager, you learn that a teammate will be out sick for at least a week. They will be unable to complete their tasks, potentially causing the project to go past its deadline. Which work reallocation strategy can keep the project on schedule? Have teammates work longer hours to get their tasks done and then do the out-sick teammate's tasks Distribute all of the out-sick teammate's tasks evenly among team members Get leadership to approve overtime so the teammate can catch up on work when they return. Review the out-sick teammate's tasks to determine which tasks have "float" and figure out where the order of tasks can be changed or resources can be juggled