Question: As a project manager, you need to develop the Project Schedule. As part of preparing the Schedule, you need to sequence and link the following

As a project manager, you need to develop the Project Schedule. As part of preparing the Schedule, you need to sequence and link the following activities:
Activity A: Onboarding Team Members
Activity B: Assigning Tasks to Team Members
What will be the correct Activity dependency between Activity A and Activity B?
Activity B can only start when Activity A has finished (Finish to Start)
Activity B can only start when Activity A has started (Start to Start)
Activity B can only finish when Activity A has finished (Finish to Finish)
Activity B can only finish when Activity A has started (Start to Finish)
 As a project manager, you need to develop the Project Schedule.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!