Question: As a project manager, you need to develop the Project Schedule. As part of preparing the Schedule, you need to sequence and link the following
As a project manager, you need to develop the Project Schedule. As part of preparing the Schedule, you need to sequence and link the following activities:
Activity A: Onboarding Team Members
Activity B: Assigning Tasks to Team Members
What will be the correct Activity dependency between Activity A and Activity B
Activity B can only start when Activity A has finished Finish to Start
Activity B can only start when Activity A has started Start to Start
Activity B can only finish when Activity A has finished Finish to Finish
Activity B can only finish when Activity A has started Start to Finish