Question: As a project manager, you need to develop the Project Schedule. As part of preparing the Schedule, you need to sequence and link the following
As a project manager, you need to develop the Project Schedule. As part of preparing the Schedule, you need to sequence and link the following activities:
Activity A: Assembly of the hardware
Activity B: Installation of the Operating System
What will be the correct activity dependency between activity A and activity B
Activity B can only start when Activity A has finished Finish to Start
Activity B can only start when Activity A has started. Start to Start
Activity B can only finish when Activity A has finished. Finish to Finish
Activity B can only finish when Activity A has started. Start to Finish
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
