Question: As the project manager for a software project that involves bleeding edge technology that has yet to be proven, you are charged with procuring the
As the project manager for a software project that involves bleeding edge technology that has yet to be proven, you are charged with procuring the right software development partner to deliver project requirements. You have already completed a request for information RFI but there remain issues that can only be solved once development has begun. What is the next step in the bidding process?Make a Single Source selectionChoose the resource that provides the lowest cost estimateIssuing an RFP request for proposal to prospective sellersIssuing and RFQ Request for Quote to prospective sellers