Question: As the project manager overseeing a technical implementation project, you have been asked by the customer to consider post - project expenses like maintenance and
As the project manager overseeing a technical implementation project, you have been asked by the customer to consider postproject expenses like maintenance and service. This scenario exemplifies which of the following?
A Operations
B Life cyde costs
C Project spin off
D Scope creep