Question: as the project manager, you decide to estimate cost using characteristics of the project historical data, and a mathematical algorithm, which type of cost estimating
as the project manager, you decide to estimate cost using characteristics of the project historical data, and a mathematical algorithm, which type of cost estimating are you using? A parametric estimating. B vendor bid analysis. C analogous estimating. D bottom up estimating.