Question: As the project moves into month 3, project manager Eric estimates the CPI = 0.7 and SPI = 0.85. Which of the following describes the

As the project moves into month 3, project manager Eric estimates the CPI = 0.7 and SPI = 0.85. Which of the following describes the project progress up to today?

Group of answer choices

A. The projects cost exceeds budget and its progress is behind schedule

B. The projects cost is below budget and its progress is ahead of schedule

C. The projects cost exceeds budget and its progress is ahead of schedule

D. The projects cost is below budget and its progress is behind schedule