Question: As you start executing a project which has been properly planned around risk management best practices, a pandemic is announced and your project is shut

As you start executing a project which has been properly planned around risk management best practices, a pandemic is announced and your project is shut-down as it involves people working in close proximity to each other. This is an example of
Question 6 options:
a)
An opportunity to re-plan the project
b)
A crisis
c)
A big risk
d)
good project management