Question: asap 6 4 The following table contains data for a project. Assume that there is significant indirect cost, implying that crashing is always worth doing
asap
6 4 The following table contains data for a project. Assume that there is significant indirect cost, implying that crashing is always worth doing Immediate Normal Crash Cost of Activity Predecessors Time Time Crashing (days) (days) A per Day 5 4 $200 B 7 S500 5 D $200 10 8 E $300 B 6 S F S400 AC 7 G S S650 B 4 H 3 S500 EDG 6 5 $350 Using the table, what is the minimum crashing cost to finish this project in 18 days? O A $3,450 8. $850 O C.51.150 OD. $1,500 O E, 50