Question: The following table contains data for a project. Assume that there is significant indirect cost, implying that crashing is always worth doing Normal Immediate Crash

The following table contains data for a project.
The following table contains data for a project. Assume that there is significant indirect cost, implying that crashing is always worth doing Normal Immediate Crash Cost of Activity Time Time Predecessors Crashing (days) (days) per Day $ 4 $200 B 7 6 S500 5 4 5200 D 10 X S300 E B 6 5 $400 F AC 7 5 $650 G B 4 3 S500 H EDG 6 5 $350 Using the table, what is the minimum completion time for this project after crashing? O A 23 days B.21 days OC 19 days OD. 17 days O E 15 days