Question: Ash is considering a project that costs R5000. It is estiated that the project will generate R10000 for year 1, R30000 for year 2 and

Ash is considering a project that costs R5000. It is estiated that the project will generate R10000 for year 1, R30000 for year 2 and r10000 fir year 3 and R12 000 for year 4. The discounted rate used is 12%. Advise Ash on the feasibility of this project.