Question: ASK IMMEDIATE PREDECESSOR NORMAL TIME(DAYS) MINIMUM TIME CRASH COST/ DAY A -- 6 4 $50 B A 10 8 $250 C -- 5 4 $200

ASK

IMMEDIATE PREDECESSOR

NORMAL TIME(DAYS)

MINIMUM

TIME

CRASH COST/ DAY

A

--

6

4

$50

B

A

10

8

$250

C

--

5

4

$200

D

C

4

1

$300

E

D

9

7

$250

F

B and E

2

1

$150

What is the total crash cost required to complete the project in 16 days?

Group of answer choices

$450

$850

$900

$650

$600