Question: Activity Immediate Predecessor Normal Time (days) Normal Cost ($) Crash Time (days) Cost Slope A - 3 50 2 50 B - 6 140 4
| Activity | Immediate Predecessor | Normal Time (days) | Normal Cost ($) | Crash Time (days) | Cost Slope |
| A | - | 3 | 50 | 2 | 50 |
| B | - | 6 | 140 | 4 | 60 |
| C | - | 2 | 50 | 1 | 30 |
| D | A | 5 | 100 | 3 | 40 |
| E | C | 2 | 55 | 2 | - |
| F | A | 7 | 115 | 5 | 30 |
| G | B, D | 4 | 100 | 2 | 70 |
Assume the indirect costs to be as follows:
| Project Duration (days) | 12 | 11 | 10 | 9 | 8 | 7 |
| Indirect Costs (dollars) | 900 | 820 | 740 | 700 | 660 | 620 |
(a) Determine the initial project duration, project cost and critical path?
(b) Find the optimum cost time schedule for the above project.