Question: Assembly component A uses 2 units of component B. Component A has 32 and 64 planned order releases that you use in week 3 and
Assembly component A uses 2 units of component B. Component A has 32 and 64 planned order releases that you use in week 3 and 4. The company expects entry of the delivery of 12 component B by using 96 component B in the inventory at the end of the 2nd week and from an external supplier at the beginning of the 3rd week. What is the net need from component B at week 4?