Question: Consider the MPS, BOM, and inventory data shown below. Complete the MRPs for Items B, C, and D. The following table shows the MPS start
Consider the MPS, BOM, and inventory data shown below. Complete the MRPs for Items B, C, and D.
The following table shows the MPS start quantities for the next 10 weeks.
| Finished Item A | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 |
| MPS start time for Item A | 20 |
| 60 |
| 40 |
| 20 | 40 |
|
|
Bill of Material:
- Item A uses 2 units of component B, 1 unit of component C.
- Subassembly B uses 2 units of component D.
Selected Inventory Data:
| Item | Lot Sizing Rule | Lead Time | Scheduled Receipts | On-Hand |
| B | L4L | 1 | 80 in period 1 | 0 |
| C | FOQ = 50 | 2 |
| 40 |
| D | POQ = 4 | 1 |
| 120 |
Construct the MRP schedule using the preceding information.
Use this template!

1 2 3 4 5 6 7 8 9 10 MRP (B) Gross Requirements (B) Shceduled Receipts Projected on hand inventory Net Requirement Planned Receipt Planned order releases MRP(C) Gross Requirements (C) Shceduled Receipts Projected on hand inventory Net Requirement Planned Receipt Planned order releases MRP (D) Gross Requirements (D) Shceduled Receipts Projected on hand inventory Net Requirement Planned Receipt Planned order releases