Question: Assembly Line Baloncing. Below are eight tasks that need to be subjected to assembly line balancing. 3 0 0 units are needed in every eight

Assembly Line Baloncing. Below are eight tasks that need to be subjected to assembly line balancing. 300 units are needed in every eight hour shift.
\table[[Step,Immediate Predecessor,Time (mins)],[A,--,0.3],[B,--,0.2],[C,A,0.1],[D,B,0.5],[E,D,0.4],[F,C,0.3],[G,C, D,0.6],[H,E, F, G,0.7]]
What is the required cycle time? Formula Required: CT=AR
860300=1.6 cycle Time
Perform assembly line balancing using the longest task time. Break all ties in alphabetical order. Only do the FIRST workstation.