Question: . ( Assign Tasks to Workers ) Consider the following six tasks that must be assigned to four workers on a conveyor - paced assembly
Assign Tasks to Workers Consider the following six tasks that must be assigned to four workers on a conveyorpaced assembly line ie a machinepaced line flow Each worker must perform at least one task.
Time to Complete Task seconds
Task
Task
Task
Task
Task
Task
The current conveyorpaced assembly line configuration assigns the workers in the following way:
Worker : Task
Worker : Task
Worker : Tasks
Worker : Tasks
a What is the capacity of the current line?
b Now assume that tasks are allocated to maximize capacity of the line, subject to the conditions that a worker can only perform two adjacent operations and all tasks need to be done in their numerical order. What is the capacity of this line now?
c Now assume that tasks are allocated to maximize capacity of the line and that tasks can be performed in any order. What is the maximum capacity that can be achieved?
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock