Question: Assigned Projects Table: A only A and/or D Assumptions: 0 Estimates are expressed in person days. 0 The Due Date provided is an end of


Assigned Projects Table: A only A and/or D Assumptions: 0 Estimates are expressed in \"person\" days. 0 The Due Date provided is an "end of the week" due date. 0 If a Resource has the necessary skills, you may assign more than one resource to a project. 0 Resource D is on vacation during Week 1. Map each project in the Assigned Projects Table above on your Project Roadmap. Use the information in the HighLevel Estimate, Due Date, and the Required Resource(s) columns to organize the work. What would you communicate? What issues do you see? Project Roadmap Week 1 Week 2 Week 3 Week 4 ProjectMTWThFMTWThFMTWThFMTWThF P1 P2 P3