Question: Assignment 04 BZ460 Project Management Calculate the ES, EF, LS, and LF times and the slack for each activity in the below and identify the

Assignment 04

BZ460 Project Management

Calculate the ES, EF, LS, and LF times and the slack for each activity in the below and identify the critical path for the project.

Can the project be completed in 40 weeks?

Assume that Activity A actually finished at 3 weeks, Activity B actually finished at 12 weeks, and Activity C actually finished at 13 weeks. Recalculate the expected project completion time.

Which activities would you focus on in order to get the project back on schedule?

Assignment 04BZ460 Project ManagementCalculate the ES, EF, LS, and LF times and

Activity B Activity E 2 10 5 7 Activity A Activity D Activity G 1 2 4 15 7 12 Activity H Activity C 8 Activity F 5 3 8 6 20

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!