Question: Assignment 1 a) Based on the data shown in Table 1 i.Produce a network diagram II. Identify the critical path and slack time for each

Assignment 1 a) Based on the data shown in Table

Assignment 1 a) Based on the data shown in Table 1 i.Produce a network diagram II. Identify the critical path and slack time for each activity. [3 M] [6 M b) Discuss briefly on the information provided for a project manager based on the critical path and non-critical path identified. [3 M] Jable 1: Task list for a distribution system project. -- Task Duration (weeks) Dependency 5 B 8 C 8 D 15 A E 6 B F 12 B G 9 C H 11 F G 1 5 H J 3 DE K 10 F N 9 IJK