Question: Assignment 12 Project Management Due Date: May 14 Thursday 1. The move to a new building for an organization has the following steps: Description Predecessor

Assignment 12 Project Management Due Date: May 14
Assignment 12 Project Management Due Date: May 14 Thursday 1. The move to a new building for an organization has the following steps: Description Predecessor Time Activity B 3 Final preparation of new space Employees pack up things to be moved Set up new office space Move employee belongings Update information systems on new phone and office numbers D C D a. Draw the network. What is the time to complete these activities and the move? b. Find early and late times, and slack times C. Find project completion time